on 2022 Aug 04 7:55 AM
The Warehouse Monitor shows GI and GR posting Warehouse Tasks with a PMR document reference (against a Manufacturing order). Seems it is wrong as this is an outbound scenario.
Request clarification before answering.
If you have posted Consumption Reversals for the Production Material Request (PMR), that is technically a Goods Receipt Warehouse Task. This is what you can see in the Warehouse Monitor.
In outbound scenario (e.g. PDO and PMR documents), consumption is related to "Goods Issue" WTs, and reversal is always a "Goods Receipt" WT (because products are again received in the warehouse).
In inbound scenario (PDI documents), receiving is related to "Goods Receipt" Warehouse Tasks, but when you reverse a GR, it will create a "Goods Issue" WT (as the products leaving the warehouse).
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.