on 2015 Dec 14 6:53 PM
Hi
We have ECC 6 Ehp 6, BW 7.31 and SCM 7.0 If we decide to move to S4 Hana 1511, to what release and Ehp would we need to upgrade SCM 7.0 ? This is because all of SCM are not available in S/4 Hana as of 1511.
Thanks!
Request clarification before answering.
Hi Bidwan,
According to the
support.sap.com/pam
SAP S/4HANA ON-PREMISE 1511 (Support Packages and Patches)
is a system with SAP_BASIS 750 (you have to go to EHP8)
in this case you must use SUM SP15 to go to this release
You can read more about it in the above link.
Best regards
Imre
please also read this http://scn.sap.com/docs/DOC-65072
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You need to upgrade to SCM 713 (SCM 7.0 EHP 3), which supports hana.
Regards,
Claire
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 8 | |
| 7 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.