Mixed resource cannot be selected when advanced planning is selected Message no. CR403

dua_dhiraj
Participant
0 Likes
840

Hi Experts,

I am new in PPDS S4 HANA. Can anybody help me out with error, generated while making tick for advance planning in work center.

Mixed resource cannot be selected when advanced planning is selected

Message no. CR403

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Likes

Hello

As stated in the following note, The Mixed Resource functionality will be available from SAP S/4HANA 2020 FPS1 release onwards:

2979647 - Mixed Resources Enablement in S/4 ePP/DS

Regards,
Caetano