on ‎2021 Apr 14 3:33 PM
Hi Experts,
I am new in PPDS S4 HANA. Can anybody help me out with error, generated while making tick for advance planning in work center.
Mixed resource cannot be selected when advanced planning is selected
Message no. CR403
Request clarification before answering.
Hello
As stated in the following note, The Mixed Resource functionality will be available from SAP S/4HANA 2020 FPS1 release onwards:
2979647 - Mixed Resources Enablement in S/4 ePP/DS
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.