Mismatch in the Purchase order Delivery date in ECC and APO

Former Member
0 Likes
744

Hi All,

For some reason the purchase order delivery date in ECC and the End date of the Order in APO is not matching. The delivery date in ECC is 07.01.2016 whereas the order end date in APO in 13.01.2015. CAn you let me know what might be the issue.

lss

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Likes

Hi Shyam

check the planned delivery time in your material master in ECC. In order to synchronize the dates between ECC and APO, the planned delivery time in ECC material master and transportation time in APO transportation lane should be the same.


Also run CCR and check once


Regards

Virender

Former Member
0 Likes

Hi Virender

Thank you for the response. The issue is we use aggregation planning in CTM. We have header article and corresponding items. ECC has only the article and in APO the planning results are viewed in terms of the item. i.e the Purchase order is created at the item level. Now the Planned Delivery time in the article and the Transportation time of the individual item in TL in apo are different.

What could be the other reasons.