on ‎2021 Apr 05 11:45 AM
Hi Experts
Please let me know if minimum resource capacity can be modelled in S/4 PPDS.
Regards
Mridul
Request clarification before answering.
Hello,
The "minimum capacity" in the planning parameters of a bucket resource used in SNP. I don't think it is supported in PPDS or S4H PPDS.
Maybe you can have a look on SAP note 2970988 - Restrictions and Implementation Recommendations for Production Planning Optimizer (SAP S/4HANA 2020)
Best Regards,
R.Brahmankar