Minimum Resource Capacity

0 Likes
228

Hi Experts

Please let me know if minimum resource capacity can be modelled in S/4 PPDS.

Regards

Mridul

Accepted Solutions (0)

Answers (1)

Answers (1)

rupesh_brahmankar
Active Contributor
0 Likes

Hello,

The "minimum capacity" in the planning parameters of a bucket resource used in SNP. I don't think it is supported in PPDS or S4H PPDS.

Maybe you can have a look on SAP note 2970988 - Restrictions and Implementation Recommendations for Production Planning Optimizer (SAP S/4HANA 2020)

Best Regards,

R.Brahmankar