on ‎2025 Jun 03 3:05 AM
I created a sales scheduling agreement using VA31, and the dates on the Forecast delivery schedule are 6/4 and 6/5, but the dates found in Stock/Requirements (MD04) are all 6/3 (today). I would like to ask how to set the date to be consistent.
Request clarification before answering.
From SD perspective, you should always check co09 and not md04. Have a look at this SAP help documentation
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @LIUYUNDI
You need to consider the last two schedule lines with confirmed quantities. Those are the lines reflected in MD04. The schedule lines dates are delivery dates. Whereas MD04 shows material availability dates, i.e. dates when materials need to be available so you can ship them on time. You can see all the dates in schedule lines details.
Best regards
Dominik Tylczynski
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 12 | |
| 8 | |
| 4 | |
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.