cancel
Showing results for 
Search instead for 
Did you mean: 
Read only

Material master changes are not reflecting on Product master in ePP/DS

shaik_adnan
Participant
0 Likes
310

Hi All

We have activated advance planning for few materials in S4 HANA 2021, product master was created for these materials in ePP/DS but some of the fields like lot size and requirements strategy (maintained in the advancing planning view) are not being transferred tp product master whereas some of the other fields like procurement type and PP planning procedure are getting transferred, any suggestions on what is missing?

Thanks & Regards

Adnan Waseem

Accepted Solutions (0)

Answers (1)

Answers (1)

aws2025
Newcomer
0 Likes

Materials were created prior to S4 1610 and guids aren't updated.