on ‎2019 Jul 03 7:54 AM
Hi All,
I have done some changes in location + product - like GR time and period factor in Active Version and I want this change to be adopted by planning in Simulation version. How it is possible ?
Will I need to do the "copy planning version" again or the simulation version will reference this change automatically ?
I want to run capacity leveling in simulation version (with new changed data in loc+prod)
Regards,
Prabhat
Request clarification before answering.
Hi Prabhat,
in case you make version independent field changes that are not included in the table /SAPAPO/MATLSIM, then the planning process will refer them from the product master.
If the fields are existing in /SAPAPO/MATLSIM , you either need to edit the product master on the relevant planning version in /SAPAPO/MAT1 or you must run indeed another version copy.
With best regards
Gergely
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.