on 2023 Jan 30 9:20 AM
Hi All,
Manufactuing order crate released, and staging is done. BOM materials are staged in the PSA locations. Once the production process done while posting goods receipt for the production order material document is generating instead of inbound delivery.
I think I am missing some configuration could you please help me in this.
c ehck the configuration.
Regards,
Chand
Hi Chand,
Can you please check goods receipt tab of your process order, storage location is missing or having correct storage location for EWM storage location.
Thanks,
Shailesh