on 2022 Oct 20 11:59 AM
Good morning.
I’m currently trying to devellop scheduling agreement for the first time in SAP.
After having created the scheduling agreement, I guess correctly, I have an issue regarding the scheduled lines.
Everything works correctly except that the schedule lines don't appear before a certain period. (01.02.2023)
I tried to modify the first delay in the scheduling agreement. (Which is I think the firm period?), but nothing changed.
I also put 2 days in MM02 for the fence horizon ("Horizon de plannif" fixe in french)
I must have forgotten a parameter.
Any ideas ?
For information, see below some screen shot of SAP.
Request clarification before answering.
If I am not wrong reading the French screenshot, you set up "planned delivery time" as 70 and that might shift the lines during MRP run. Please try to reduce this and see if it changes the result.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
5 | |
4 | |
4 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.