Issue with Planned Price transfer from sales history in S/4 to IBP via CPI

ydyulgerov
Participant
0 Likes
282

Hello everybody,

my question refers to the Planned Price key figure. I would like to transfer planned price from sales history from S/4 to IBP via CPI and I am using the standard template available in CPI. I have done the mapping as described in SAP Help - IBP_KF_PlannedPrice . The issue is that the CPI is reading all the data needed. I checked that via the View-time design data option. However, the job finishes successfully, but no data is transferred.

Furthermore, when I checked Data Integration Job App in IBP, I found out that there are also 0 records.

I am attaching a few sceenshots from the CPI.

Thank you very much in advance.

BR,
Julian

1.

2.

3.

Accepted Solutions (1)

Accepted Solutions (1)

ydyulgerov
Participant
0 Likes

Hello everybody,

I managed to find my mistake on my own. I did not put the right name of my planning area within the global variables definition...sorry for creating this new topic, but this could also be beneficial for others. Always take another look into details! 🙂