I try to execute a Maint. plan using tcode IP30.

When it was executed it shows the next "Date: 01.02.2026 error is after the end of factory calendar MX; Maint. plan".

I read some articules related with this and says that I have to change the end date of the factory calendar that I'm using in SCAL.

I did but the error continues.

I checked also the factory calendar that uses my center in tcode OX10, and is correct.

Can anybody help me??

Accepted Solutions (1)

Accepted Solutions (1)

peter_atkin
Active Contributor
0 Likes

It should look something like this:

0 Likes

There is exists a way to update the holidays in the next year.

I mean how can add the holiday days in 2026.

I really appreciate the help

Answers (4)

Answers (4)

0 Likes

There is exists a way to update the holidays in the next year.

I mean how can add the holiday days in 2026.

I really appreciate the help.

peter_atkin
Active Contributor
0 Likes

In the SCAL image above you are showing the Public Holiday calendar.

Choose the Factory Calendar option and ensure the calendar is extended more than 61 Months..

.

PeteA

0 Likes

The factory Calendar is until 2035 .

But I think it's because I didn't assign the days in the end year (2026)

Left it's prod and right it's dev. When we did some tests on dev enviroment it works great. I think that's why on prod enviroment doesn't work yet.

peter_atkin
Active Contributor
0 Likes

What is the Scheduling Period set to on the Scheduling Parameters tab in IP03?

PeteA

0 Likes

Is the next one

peter_atkin
Active Contributor
0 Likes

Bernardo,

Try going into IP10 for the and plan click on the Update Scheduling button at the bottom of the screen. Does that give any errors?? If not, then re-run IP30 for that plan.

If there is still a problem, then send a screen-shot of the MX calendar in SCAL.

Note: factor calendars are used for order scheduling in the following objects:

  • Maintenance plan Scheduling Parameters screen
  • Order header and operation work centres
  • Order header calendar in the Dates screen area (Note: this field may not be displayed depending on whether you have the relevant Switch activated)

.

PeteA

0 Likes

Hi Peter.

I tried what you wrote but is wasn't successfully.

The Update Scheduling button appears disabled in the plan.

I shared you the images. I pressed the button start but shows also the same error.

0 Likes

An this is the Factory Calendar MX

peter_atkin
Active Contributor

Can you please send a screen-shot of the MX factory calendar in SCAL

PeteA

0 Likes

About the Holiday Calendar is the next one