Invalid time while creating Planned order for component in CDP

0 Kudos
308

sap-apo-cdp.jpg

Hello Team ,

As i have been trying to implement CDP, and i have assigned the Planning Procedure as 3 for KMAT and Components and also set X0 MRP type. When i create sales order for configurable material, CTP run but ends with error of Invalid time interval

All the PDS /BOM with object Dependancy are CIFED to APO

Kindly help in resolving the issue

Accepted Solutions (0)

Answers (2)

Answers (2)

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Invalid time interval" Message No. /SAPAPO/OM011

Make sure that a PDS or PPM is valid on the date of order explosion with valid mode.

Best Regards,

R.Brahmankar

0 Kudos

Thanks Brahmankar,

Issue resolved , as the ATP check group was not populated in Product master for the components.

Thanks

rupesh_brahmankar3
Active Contributor
0 Kudos

Hello,

Thanks for sharing the solution, please close the question.

Best Regards,

R.Brahmankar

angelg_reyes
Explorer
0 Kudos

Take a look to OSS Note 1287148 - Integration PO to APO - Error 'Invalid time interval'.