on ‎2019 Dec 01 10:56 AM
Dear All,
I would like to understand if there will be a direct link between IBP and MRP in SAP S4 HANA?
Can there be a link where MRP when executed for a Material, can consider the forecast provided by SAP IBP and then generate requirements and in turn a PR for that material?
Regards
Prasanna
Request clarification before answering.
Hi,
It depends on the business case.
Forecast generated in IBP (S&OP or Demand) then transfer to S/4HANA, S/4HANA MRP or MRP live run for those materials as a daily background job and generated the planned or purchase requisitions.
Forecast generated in IBP and release to Supply & Response for supply planning. After planning planned orders and purchase requisitions transferred to S/4HANA. If IBP planning results transferred to S/4HANA weekly basis or monthly then MRP can take care of net change planning run.
Best Regards,
Lingaiah
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Lingaiah,
Thanks a lot for the response! Highly appreciated!
"Forecast generated in IBP (S&OP or Demand) then transfer to S/4HANA, S/4HANA MRP or MRP live run for those materials as a daily background job and generated the planned or purchase requisitions."
Could you please help me out on how the above-mentioned integration between IBP and MRP works? Are there any specific configurations to be done?
It would be great even if you could point me out to any SAP notes or blogs. I tried searching but couldn't find any.
Regards,
Prasanna
| User | Count |
|---|---|
| 16 | |
| 16 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.