on 2022 Sep 30 2:55 PM
Hello,
System created inspection lot, typr 1708, and usage decision has been recorded with automoticj follow up action.
But this last action created warehouse task, I want to aviod this wt. How I can change it?
Best regards.
Request clarification before answering.
Hi mestansahin
Go to the path Extended Warehouse Management --> Cross-Process Settings --> Quality Management --> Inspection Results --> Maintain Follow-Up Actions --> Assign Logistical Follow-Up Actions --> select the follow-up action and click on "assign logistical follow-up actions".
Here, you can change the "int. follow-up action" from "Putaway" to "Posting change" only.
When usage decision is taken, then the "posting change" makes the stock type change from quality to unrestricted only. It will not create putaway tasks.
Best regards
Janardhan S Musigeri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
5 | |
4 | |
4 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.