Hello EWM experts


I have a standard calendar for my warehouse with 5 working days (mo - fr). Additional I have a second one with 7 working days including holidays.

In my wave template I used my second calendar (mo - su) and it is found during wave assignment, but weekend is still ignored and the wave is created for Monday.

Thanks for help!

BR
Raphael

Accepted Solutions (0)

Answers (1)

Answers (1)

Ajit_Routray
Active Contributor
0 Kudos

Hi rapha_de,

Could you try with no calendar in wave template please. I guess system should not consider any calendar, create/release wave for 7 (Mon-Sun) days including weekend.

If blank calendar set up works, then check for newly calendar if any thing missing.

Please let us know if you have further queries.

Kind Regards,

Ajit

rapha_de
Discoverer
0 Kudos

Hi Ajit,

Thanks for your response. I already tried with no calendar in wave template, but the outcome was the same.

The description in F1-Help says that it should not take into account any calendar if the calendar field in template is empty.

KR

Ajit_Routray
Active Contributor
0 Kudos

Hi rapha_de,

Ohh sorry ..as per my understanding ..looks like a bug if your set up is fine and guess no release days in wave template....If possible ..Please share the wave templete..

What is your EWM version ? Is delivery date past ?

I checked wave planning code, found something different..might be in line no 44.

Kind Regards,

Ajit

rapha_de
Discoverer
0 Kudos

Hi ajit.routray.ewm

This is my opinion too. I opened a OSS Ticket at SAP and wait for response.

We have 9.5 and delivery date is in future on Sunday. In wave template is also no additional day for cutoff, release, etc.