Experts,
We are using S4 1610 version. When we switch SOS/PDS in PPDS, via the Planning board the following happens:
Planned Orders are created from S4 & SOS/PDS change is triggered from Planning Board. Conversion of Planned Orders is also triggered from PPDS.
Any clues?
Request clarification before answering.
#2403565. Hope it helps!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This was another programming bug b/w S4 & PPDS. A note helped us fix this.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.