In ECC (MD11) & APO (RRP3) planned orders are not matching production time not similar? Should the both be same or they can differ in their respective environments? If they should be similar how to do it?
Request clarification before answering.
Hi Rakesh,
You may execute the Delta Report (/SAPAPO/CCR) for Planned Orders to see if it recognizes the difference in content and allows you to resend the order to APO or ECC in order to make the dates consistent.
In /SAPAPO/CP3, it is usually recommended to create an entry for In-House Production with the setting Always Retransfer. With this, if you change the Planned Order on ECC and save, when it is sent to and automatically rescheduled in APO, APO will send the order back to ECC with its current dates - this helps prevent different dates between the systems.
Other than that, there are some scenarios where date differences may differ due to modeling and master data settings. Examples:
Regards,
Tiago
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
6 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.