Hello Carlos,
This issue might be related to the Time Profile Attributes, such as: DAYWEIGHT, WEEKWEIGHT and MONTHWEIGHT. It is likely that they are not assigned to the Planning Levels whereas they are assigned to some Key Figures, therefore it causes the issue.
You should either
1) Assign these Attributes to the Planning Levels;
2) Remove these Attributes from the Time Profile;
Best regards,
Matheus