Hello,

i have one version and two scenarios. After the what If analyse, I want to copy the result from my scenario in the baseline scenario. but only one key figure and with a filter (determine product-customer combiantion)

I know three options to do this.
1.) manually with copy and paste in a planning view
2.) with the option to choose "promote" in the excel add on. but with this option all different values will be "copy" from the szenario in my baseline

3.) with the version- and scenario copy operator. But with this operator I can only copy values from my szenario into the baseline, if my scenario in another version.

Give it further, additional options, to copy a sceanrio in the baseline scenario. Remember, I have only one version and with determind key figure and customer - product combinations.

Regards

Oliver