hi team,

we want to plan in excel addin for 10 years from now .

we are using S&OP ADDIN for excel, version 3.0.4.1

existing time profile is till 2040

default display horizon future for granularity year was 5 , now changed to 10 .

we have maintained from WMQY Changed accordingly in proportion to other granularity.

After executing excel add-in , filter-in TIME PERIOD -drop down we can see till 5years for planning unable to select beyond 5 years.

do we need to maintain any global parameters.

can you please suggest.

Accepted Solutions (0)

Answers (2)

Answers (2)

piyush_parekh
Active Contributor
0 Kudos

I think you've updated horizon in time profile. You need to change Planning Horizon in planning area fiori app to 10 years in future. Activate the planning area, re-login to SAP IBP Excel Add In and check.

Regards,

Piyush

Irmi_Kuntze
Product and Topic Expert
Product and Topic Expert
0 Kudos

a) have you enhanced the load of the Time Profile?

b) have you enhanced the horizon in the planning area setting?

former_member213946
Participant
0 Kudos

hi Irmhild,

a) we have already loaded time period load till 2040.(one time activity)

b) in planning area setting for time profile , default display horizon future for granularity year was 5 , now changed to 10.

as we are unable to plan in add-in till 8 -10 years from now .

Irmi_Kuntze
Product and Topic Expert
Product and Topic Expert
0 Kudos

no there is no global parameter

the only things you need is

- enhance in the TP configuration the settings in the header with the from and to DATE, activate TP

- load new file for TP with the enhanced horizon

- adjust in the planning area configuration (NOT the TP configuration, that is only the default display value in Excel) the TO period for the bucket YEAR

- activate planning area

If you did all that, you may try with deleting the meta data / cache in your Excel planning view

If that all does not help, you minimum need to post screenshots of your settings. But if you really did all that correctly, you would need to open an OSS ticket as without look into the system I have no further idea