In my example below after running the S&OP operator DEPENDENTDEMAND is not propagated as per the lead time in supply location.

Location 1 supplies to Location 2 - But the dependent demand appears in same week. Although I set the TLEADTIME as 7 days. (My base time profile is in days)

Accepted Solutions (1)

Accepted Solutions (1)

former_member242371
Contributor
0 Likes

Hello,

LEADTIME is an integer type attribute considered only by Supply operator to offset the demand bucket wise. TLEADTIME is decimal type attribute as KF and can contain fraction value. It is considered by Inventory optimization to propagate the forecast and variability to internal nodes.

Thanks,

Rohit

Answers (2)

Answers (2)

Former Member
0 Likes

Thanks for your inputs - Lingaiah.

Location 1 is supplying to Location 2.

I found that TLEADTIME has no effect on DEPENDENTDEMAND. But rather LEADTIME is used from SOURCELOCATION.

Anyone has idea why ?

lingaiahvanam
SAP Champion
SAP Champion
0 Likes

Hi,

S&OP operator is working fine. Can you check the location product and location source master data properly once again and rerun planning run.

Location 1 & 2 are DC's or can you explain the demand and supply flow.

Best Regards,