on 2020 May 07 8:29 AM
Hi all,
We have noticed that in IBP Response, HWORKDAY is equal to 1 for all periods, is there any logic to make this Key Figure only to be 1 for actual workdays? Based on the plant calendar?
Thanks in advance
Request clarification before answering.
Hi Carlos,
This key figure is only used in L code script of Key figure DAYSOFSUPPLY Calculations. So if you want to influence calculation of this key figure then use HWORKDAY otherwise its irrelevant.
Thanks
Girish