cancel
Showing results for 
Search instead for 
Did you mean: 

IBP Production Receipts disaggregation does not equal Production Receipts Adjustment

peterro
Discoverer
0 Kudos
642

Hi,
For quantity-oriented key figures in supply planning, for example, CONSENSUSDEMAND, INDEPENDENTDEMAND, PRODUCTION, RECEIPT, or SUPPLY, the S&OP planning operator uses a dedicated PeriodWeight time split policy for each key figure to aggregate and disaggregate its values. However I would like to disaggregate from calendar week level to technical week based on the adjusted production receipt. Do we have any option to disaggregate based on an other key figure values?
If the planners are maintaining the values on monthly level or even technical week level, we can not generate the same plan.
Do you have any idea for the resolution?
Thanks in advance!

View Entire Topic
peterro
Discoverer
0 Kudos

Hi Irmi,
Thanks for the help. Article helped to realize that if we get the values from the copy-disagg operator then the disaggretion method will be used. If we get the values from the Supply planning algorithm then we can use only the Time split policy. So we need to add one more step after the Supply planning run.
Thanks,
Peter