We have production versions that in ECC have minimum lot size and maximum lot size as a restriction.

IBP Supply has within the Production Source Header structure, lot sizes restrictions that are not based on lots (production events as in ECC), but are defined as a time bucket restriction. Additionaly, for each production version having a lot range in ECC, resource consumption is tight to a fixed time independent is production was at the minimum level, maximum leverl, or between them.

1. Is there a standard solution or suggestion of how to model this scenario in time-series planning?

2. Since Order based planning is based on orders, are this restrictions working as expected per production event?

Regards.

Accepted Solutions (1)

Accepted Solutions (1)

lingaiahvanam
SAP Champion
SAP Champion
0 Kudos

Hi,

I could not find the standard solution for the production version selection based on lot sizes as ECC does. Time series based planning works based on bucket consumption. I would recommend raising an incident to SAP Product Support for this requirement.

Best Regards,

Lingaiah