IBP - MOQ for KF RECEIPT

Former Member
0 Likes
750

Dear community,

could anybody tell me how to model in IBP S&OP a normal MOQ parameter for KF RECEIPT (Unspecified Receipt/External Procurement)?

Thank you.

Accepted Solutions (1)

Accepted Solutions (1)

ankpatel
Contributor
0 Likes

Hi Juan,

You can use MINRECEIPT to model MOQ for External Receipts.

Regards

Ankur

Answers (2)

Answers (2)

Former Member
0 Likes

Hi Matheus,

thanks for the answer.

Agreed with that, although that's not exactly a normal MOQ.

Cheers

Former Member
0 Likes

Hi Ankur,

thanks, but in that case: if I input a MINRECEIPT for whole horizon, it would create RECEIPTs for each of the time buckets, which is not we we want. Is that want you meant?

Thanks

mkorndoerfer
Product and Topic Expert
Product and Topic Expert
0 Likes

Hi Juan,

If you don't want RECEIPT for the whole planning horizon, then you should simply not add values for MINRECEIPT in all planning horizon - you just add in the required periods.

Also, if in some periods you want to make sure that no RECEIPT will be generated, you may use Key Figure ADJUSTEDRECEIPT and set it to 0 in those periods.
See Help Portal Adjusted Key Figures.

Best regards,
Matheus