IBP minimum lot size forecast constrained

carlos_perez8
Participant
0 Likes
454

Hi

All when running Response Constrained Forecast with optimizer, when setting up minimum lot sizes, the results are not goods, and the systems does not use semifinished in stock because of minimm stock.

Does anyone use response otimizer?

Accepted Solutions (1)

Accepted Solutions (1)

lingaiahvanam
SAP Champion
SAP Champion
0 Likes

Hi,

Optimizer does not respect the Minimum Lot Size configured.

  1. Check if the detailed discretization horizons are set to 0
    • This disables the discrete decisions and thus the optimizer will not respect the Minimum Lot Size
  2. Check the optimizer profile and delete those 0 discretization horizon-values
    • Make sure that they are null/empty afterward

Note:

  • Minimum Lot Size behavior is: either nothing is produced at all, or, in case a production takes place, at least the specified amount will be produced (in your case 400). So if there is no production at all, this does not mean that minimum lot sizes are not respected.
  • To force a minimum production of at least ## please use the Minimum Production Receipt key figure

Best Regards,

Lingaiah