on 2020 Feb 06 11:22 PM
Hello Experts,
Has anyone worked on Cyclic Low Level Code scenario in IBP? I would like to unsderstand how to build a logic to identify Cyclic LLC scenario using Key Figure calculation. We have 5 level deep Low Level Code. Note: We only have S&OP module. I cant use any standard functionality of Supply,IO or Response modules.
Thanks
Request clarification before answering.
IBP TS heuristic does not support cyclic Location Source or Cyclic Production source item, it will fail if such master data is maintained.
Take the supply planning TS Heuristic run and it will identify the cyclic Lanes / BOMs and then you can correct them.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Girish,
Thanks for your inputs.
There is LOOP_HANDLING global configuration parameter that allows you to set how cyclical sourcing in algorithms (loops) are handled in inventory optimization. We don't have Inventory Optimization license. Will it be possible to build this logic using Key Figure Calculation? I tried setting up Attribute as key figure to check LLC and find out Location From for this scenario but its difficult to trace back Location from for multi level LLC e.g. 5
Thanks
| User | Count |
|---|---|
| 12 | |
| 10 | |
| 8 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.