Dear SAP Experts
Hello.
When the delivery date of a component is pushed back, we want to revise the production plan for semi-finished products produced using the component and finished products produced using the semi-finished products in a batch.
I know that this is possible by using Heuristic Rescheduling: Bottom-Up for Conti- I/O, but the plan is not revised until the last finished product.
Is heuristic customization not a good idea?
Should we use a different heuristic?
I would like your advice.
I report in the attachment the situation that is not working.
Best regards
Nagase