Hi, does anyone know where to set the setup activity indicator in the PDS (Screenshot) I can’t find an option to do this in either S4 part or the PP/DS part. In the Operation I could only set the setup group. 44ae5825-d2d9-40d5-b3a7-696b7dcd14e6.jpeg


I tried to follow the steps provided https://authn.hana.ondemand.com/saml2/sp/mds

Accepted Solutions (1)

Accepted Solutions (1)

Sasi2005
Contributor

Hi Daniel,

I was not able to open the link of steps provided. However I suppose you are trying to use the transaction /sapapo/curto_edit to edit the PDS. Please note there are very very few fields that can be edited/updated using this transaction. You cannot edit or change the setup activity using this transaction.

On the S4 side I hope your work center has a setup activity and a relevant formula associated with it and the formula is scheduling relevant. Once done, make sure you populate a value for the setup activity which is part of the operation in the relevant routing.

Use the transaction curtoadv_create to generate the PDS. It should have then setup activity populated in the PDS .

Please check and let us know if you succeed, else please provide screen shots of routing/operation and work centres on the S4 side.

Regards

Sasi

Daniel_Degenhardt
Product and Topic Expert
Product and Topic Expert
0 Likes

Hi Sasi,

thank you exactly so the problem was that in the work center the formula was not maintained! 🙂 After I maintained that and transported it again, it worked.

Best Regards

Daniel

Answers (2)

Answers (2)

rupesh_brahmankar
Active Contributor

Hello,

PDS transfer can only detect that it is a Setup Activity if the matrix has been assigned to the Resource

Please check the Setup Matrix has been assigned in /SAPAPO/RES01 to the Resource

Then do an initial transfer of the PDS via CURTO_CREATE and check the PDS data.

This is how it wrorks in APO not sure about S4 PPDS.

Best Regards,

R.rahmankar

Daniel_Degenhardt
Product and Topic Expert
Product and Topic Expert

Hi R.rahmankar,

Yes, as you said, it has worked 🙂

rupesh_brahmankar
Active Contributor
0 Likes

Thanks a lot for sharing the feedback.

Best Regards,

R.Brahmankar

former_member567734
Discoverer
0 Likes

Hi guys, I ran into such a problem in S/4HANA cloud, formula is in resource, set value is in work sheet operation, setup matrix is tied to resource, but there is no setup indicator in the PDS and setup time from matrix is not pulled up, someone knows what is the matter ?

BR, Dmitry

Daniel_Degenhardt
Product and Topic Expert
Product and Topic Expert
0 Likes

Have you entered a value for the set-up time in the routing? Otherwise store 1 second - the value should then be overwritten.