on 2023 Dec 28 9:01 AM
Hello dears.
Merry Christmas for all.
I am new in the community and working mainly in SAP using Maintenance modules.
I have a question related planning using "Call Horizon" in the MP that contain multiple MI.
The MP cover the different maintenance strategies for each equipment, like 6M, 12M and 48M inspections.
Also we set Call horizon as 50% to trigger the activities early, specially for 48 M, where we use spare parts and allow procurement to be ready for this task.
See below:
But, when the MP start, it does not reflect our expectation, it just show the call date 3 months before the plan date, for all activities. See below:
Question: it is possible to set the "call horizon" in the way that all call for MIs show the call date at 50 % of the cycle?
For 48M: call date, before 24M plan date.
For 12M: call date, before 6M plan date
For 6M: call date, before 3M plan date.
I believed that SAP is a powerful tool that can allow this strategic.
I appreciate your help and support.
Best regards
Fabian Sanchez
Request clarification before answering.
User | Count |
---|---|
6 | |
5 | |
4 | |
3 | |
2 | |
2 | |
2 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.