Hi,
Scheduling of multiple product on single work center is a challenge for me right now. please suggest if any solution
Request clarification before answering.
Hello
Can you please describe your issue in more detail? Why is this a challenge for you?
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
currently i am unable to plan multiple product on specific work center at same time. as CM21 does not allow to schedule multiple product on one work centre.
Details: My work center is my machine with multiple section, and i can plan different product in each section as and when required.
Work center is glass manufacturing machine
and product is glass bottle
(sometimes i plan two almost identical bottles on same work center at same time)
Hello
You can create individual capacities for your work center and use the proper profile to plan the individual capacities in transaction CM25. Another alternative is to use the Shop Floor Dispatching and Monitoring Tool, that is an Add-On for the SAP ERP and focus in the individual capcities.
Regards,
Caetano
Mr. Caetano,
I have checked the scenario using the individual capacities option of work center and spitting function.
and while creating order changed the split number and planned multiple product at same time and on same work center.
successfully tested the scenario.
thanks for your revert on the query.
| User | Count |
|---|---|
| 18 | |
| 16 | |
| 5 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.