How to plan multiple product on one work center in SAP S/4 HANA

Former Member

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Likes

Hello

Can you please describe your issue in more detail? Why is this a challenge for you?

Regards,

Caetano

Former Member
0 Likes

currently i am unable to plan multiple product on specific work center at same time. as CM21 does not allow to schedule multiple product on one work centre.

Details: My work center is my machine with multiple section, and i can plan different product in each section as and when required.

Work center is glass manufacturing machine

and product is glass bottle

(sometimes i plan two almost identical bottles on same work center at same time)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Likes

Hello

You can create individual capacities for your work center and use the proper profile to plan the individual capacities in transaction CM25. Another alternative is to use the Shop Floor Dispatching and Monitoring Tool, that is an Add-On for the SAP ERP and focus in the individual capcities.


Regards,

Caetano

Former Member
0 Likes

Mr. Caetano,

Thanks for the reply. Will check the same in CM25 and revert

Former Member
0 Likes

Hi,

I have checked CM21, CM25 & CM27. But not even a single allows me to plan multiple product at a time. (Parallel jobs on same work center).

Is it possible to configure anything on routing level or work center level to accommodate multiple products on single work center at a time.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Likes

Hello

First you must define the number of individual capacities in your work center, then you should use the correct profile, such as SAPSFCG005

Regards,
Caetano

Former Member
0 Likes

Mr. Caetano,

I have checked the scenario using the individual capacities option of work center and spitting function.

and while creating order changed the split number and planned multiple product at same time and on same work center.

successfully tested the scenario.

thanks for your revert on the query.

Answers (0)