on 2015 Nov 02 11:02 AM
Hi Gurus!
We are trying to work with Late Deliver Cost or Maximum Late Delivery but we can't find any related Key Figure. ¿How can we work with this constraint in SAP S&OP?
Many thanks in advance!
Regards,
Request clarification before answering.
Hi Albert,
You can use CONSDEMLATEDELIVCOSTRATE for late delivery cost rate or CONSDEMLATEDELIVMAX for maximum late delivery periods. More information is available in application help-
Key Figures for Supply Planning - SAP Integrated Business Planning - SAP Library