In PPDDS I need to move all orders plus a interval of time. For example if the planned order starts at 12 move to 12+t for every order on a group of resources i don't want to change the spacings just push all back
Is there any other way than select all and drag and drop with the control key depressed?
Request clarification before answering.
Hello,
In DS board /SAPAPO/CDPS0 for your DS strategy define specify date, so while rescheduling system will ask you for a date and time.
Best Regards,
R.Brahmankar