Hello,
You can define the Maturation time in Product Master /SAPAPO/MAt1 please read F1 help
The period required by a product after production before it can be used for further production or by a customer.
Please refer useful SAP help link,
Shelf Life Data - Production Planning and Detailed Scheduling (PP/DS) - SAP Library
Or you can also use the goods receipt processing time
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
In the product master, you must activate indicator 'Planning with shelf life'. Only then the system includes shelf life and maturation time.
The maturity date that is defined in the product master, is copied over to all product receipts (production order, stock transfer order,...) that are generated by APO. The maturity date of a product receipt is taken into account during pegging.
Customize the stock on hand macro to adapt the maturation time.
Please refer these useful links
Planning With Shelf Life in SCM - Supply Chain Management (SCM) - SCN Wiki
Shelf Life Planning in APO - Documents
Best Regards,
R.Brahmankar
| User | Count |
|---|---|
| 16 | |
| 16 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.