on ‎2018 Aug 21 8:47 PM
Hi SAP Community,
I'm trying to integrate Production Orders and Planned orders to SAP IBP using Time Series Supply Optimizer. The thing is that I really don't know how to integrate this two differents kind of orders to the production plan.
My first idea was bring the Productions Orders to the key figure "Inventory Correction", and Planned Orders to "Minimun Production Receipts" (considering that these orders belong to the fixed plan). Nevertheless I have two questions:
1. If Production Orders yet not consumed raw materials, how can I discount these quantity in my stock of raw materials? Do should I take some status in the orders to notify the consume?
2. If Productions Orders goes to Inventory Correction, may IBP use the available capacity to planning new orders, using the available capacity, even when in reality there's a production order using it? (thinking that when the production order goes to inventory correction will not use capacity as planned order does).
Thanks for your help. Renato
Request clarification before answering.
what is complete requirements why you want to integrate supply from ERP/S4 to IBP. Standard process is to get demand from S4 and then develop supply in IBP and send back as planned independent demand to S4 then run MRP to generate planned order/purchase requisition.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 14 | |
| 9 | |
| 7 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.