How to include MRP parameters for project segment in PPDS

marcin_cieslak
Explorer
0 Likes
556

Dear PPDS Experts,

I have a scenario when I use PPDS for planning in a project segement. What I need to achieve is that MRP parameters are considered during the planning for project segment. For ERP the setting was in the lot sizing procedure procedure as shown below:


In PPDS we can also find this setting, as shown below:


Question: How, in embedded PPDS, make this field selected in /SAPAPO/MAT1

Thank you in advance,
Marcin

Accepted Solutions (1)

Accepted Solutions (1)

marcin_cieslak
Explorer
0 Likes

Dear all,

Actually I managed to find the answer by myself. Correct setting is '2' in lot sizing procedure. in OMI4. See note

2447274 - Lot-Size settings are ignored in MTO and Project segments.

Answers (0)