on ‎2025 Feb 07 1:42 AM
I would like to make a production plan using the production version in one material code.
I'm trying to plan using multiple cases at once rather than a single product code, can I add a production version field in Excel upload in the PIR maintenance app?
If you can upload the quantity required for Excel through the production version with an app other than the PIR maintenance app, please let me know the app name
thank you.
Request clarification before answering.
Hello Kimminah,
unfortunately the maintain PIR app does not support the production version. At the moment, there is also no possibility using the API for S/4HANA Public Cloud. The API also does not support production versions for PIR.
Regards Johannes
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 15 | |
| 5 | |
| 5 | |
| 3 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.