How to do capacity plan in long term

siegfried0530
Discoverer
0 Kudos
194

Hello,

right now I'm doing long term capacity planning, is there any way to check the capacity of an certain Work center in 10 years horizon, similar as CM01 (only in longer olaning horizon)? 

Accepted Solutions (0)

Answers (1)

Answers (1)

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hello

If you are using SAP S/4HANA, then you can load inactive PIRs and use the Predictive MRP simulations to evaluate the work center capacity (I wrote a SAP Press e-book about pMRP that might be useful :D).

If you are still using ECC, you can use a Long-Term Planning scenario, load inactive PIRs and use transaction CM38 to evaluate the planning scenario capacity. You might have to create a different profile with a longer time horizon. 

Best regards,
Caetano