How to design Storage location for Raw material consumption to production order

0 Kudos
208

For Customer Business, they have scenario for raw materials 2 groups

Group 1 : Raw materials which use for release to production order type of Engineering Test or Pre-Production Testing group.

Group 2 : Raw materials which use for release to production order type of Mass production group.

Let's say business need to purchase materials to Main Warehouse before doing stock transport order to Plant.

After Plant receive both of material from Group 1 and Group 2 then it need to distribute materials to each team for manage stock and release production order. (ex , Group 1 manage stock by Team A , Group 2 manage stock by Team B)

In physical material control, It can be keep for 2 places such as

Group 1 : physical material keep in Room A - Manage by Team A

Group 2 : physical material keep in Room B - Manage by Team B

When PP team created production order, There need to design BOM for material group 1 and material group 2 separately.

Does it need to be design storage location for raw materials group 1 and group 2 separately?

Because it should not be design only 1 storage location for different kind of BOM for both of group, Is that correct?

Accepted Solutions (0)