on ‎2021 Jul 02 11:21 AM
Hi All,
I have a typical requriement. When the planned order is created in the APO system, it should confirm the quantities and ATP quantities should be reduced to the extent of planned order quantity.
In ECC system, I am able to do it by activating the check box 'Activate full confirmation logic' for the MRP group, with planned order created in ECC system. As a result of it, the ATP quantities are updated in the CO09. But when the planned order is created in APO system then ATP quantities are not updated, for the same loaction product combination.
Can any one help?
Thanks & Regards
Piyush Ranpura
Request clarification before answering.
Hello,
You can check the following PPDS customization
Production Planning and Detailed Scheduling (PP/DS)-->Global Settings-->Maintain Global Parameters and Defaults
In the Execute tab you will find "Correlation Calculat. Mode" in APO this controls this behavior. Unfortunately its a global setting.
F1 help is very good and explains its function very well.

Regards,
Abhishek
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
For APO managed products you can use /SAPAPO/RRP8 - Perform ATP Check for REM Planned Orders
report /SAPAPO/RRP_ORDER_ATP_CHECK,
Also BAdI /SAPAPO/RRP_ATPCHECK can help for customer specific requirements.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 4 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.