on 2023 Jun 08 8:37 AM
For a simple supply chain network for a product PROD1 in Plant and DC and Component COMP1 in Plant which should get from vendor .
Created TLane between DC to Plant
Created PDS for PROD1 in Plant with component.
when I ran the Supply run ,orders are not created giving the gating factor as No source of supply for COMP1in PLANT is detected
I have maintained TLANE from VENDOR to PLANT for COMP1
Now Supply run gave the gating factor No source of supply for COMP1 in VENDOR
How can we close this network as we don’t need where Vendor is procuring or producing?
Note: when we created PDS for COMP in VENDOR location it created orders which is wrong.
Request clarification before answering.
Hi Ravindra,
Have you created the Raw materials at Vendor Location in your Location Product Master data? It is not desired in IBP OBP for a location type 'V'.
Please delete Location Product MD entry for Component Vendor combination and rerun your supply planning algorithm?
Regards
Gaurav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.