on 2016 Feb 04 10:57 AM
Hello,
we use heuristics to create our stock transfer requisitions for snp.
If the start date of a requisition would be scheduled in the past the scheduling does a forward scheduling and
creates the purchase requisition by forward scheduling.
This leads to the fact that the purchase requisition is too late.
In SAP ECC MRP it is possible to avoid this by setting a flag in the IMG "Parameters for Determining the Basic Dates".
My questions, where I did not find an answer until know:
- Is there something similiar possible for heuristics run?
In case not:
- Is it possible to suppress the creation of purchase requisition in cases where those would be too late to fulfill the requirement?
Thanks in advance!
Heinz
Request clarification before answering.
Heinz,
In SNP if you would like to have a stock transfer have a start date in the past in backward scheduling, you need to use a BAdI which can be setup to run only for particular matches of location-product combinations. For Ex: SNP Planner.
BAdI: /SAPAPO/SNP_HEU
Regards
AK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 12 | |
| 11 | |
| 8 | |
| 2 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.