on ‎2021 Jun 02 8:00 AM
Hello, Everyone I need your help.
Our company is currently using SAP APO Module. ERP MRP is executed twice at dawn.
There is a problem here, In Production control team, who if the purchase order is issued from SAP ERP to
me21/me21n at morning time (after dawn) immediately, purchase order is forced from the APO. (3min) If the
production team doesn't run the heuristics on the APO, at this time, the point of purchase team view PO/PR
appears at the same time. (It's doubled) The purchasing team will look that till the MRP runs.
So, we'd like to place an automatic order.
In My question, Can't we automatically remove the Pr and leave only the PO from the APO when the purchasing team generates the PO at the ERP? Due to this problem, we can miscalculate the pr and place an order. ↓↓

Request clarification before answering.
Hello,
Are you creating a manual PO? Why are you not converting PR in to PO?
As your heuristic already created the PR and you planning team manually creating PO then it will be double the supply.
Or if you want to continue same practice then schedule the heuristic backround job in APO after PO created by planning team.
Best Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 3 | |
| 3 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.