How to acheive partial bin to bin transfer using RFUI in EWM?

Former Member
0 Kudos
950

Scenario is; 1 Hu in storage bin X has 20 pcs,I want to move 1 pc to storage binY.but there is no existing HU in bin Y so i expect the HU to be create automatically.The same can be achieved in /SCWM/PACK under Repack product tab but i am unable to find the same functionality in RF screen please help.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member

Thanks for your reply marek.

MarekKaminski
Contributor
0 Kudos

Hi,

Please try move the HU to the packing work-center (by ad-hoc WT) by using RF.

Then go to the "packing" in RF, you can maintain empty HU there, and re-pack the item from the eariler moved HU to the newly created one.

It is a lot of steps but it is possible by RF.

Best Regards,

Marek