on 2018 Sep 24 8:00 PM
Hello Expert
My Delivery date on STO is calculated automatically.
The system give me Delivery date = day of sto creation + 1.
How can i control that please? any field to fill on material master data?
Regards
Ghita
It is based on your material master MRP-2 view where you can see fields like "In-house production" and "GR processing time". If you have info record, then, it depends on that also.