Dear all
We have 2 materials which should always be produced together on the same work centre and are produced to anonymous stock. It may happen that both production orders should be rescheduled automatically e.g. because of planned maintenance, or because in a certain slot capacity overload exists. In the planning table in S/4HANA (transaction CM25) we could not find a way to reschedule automatically both production orders at the same time and move them together to the next available slot (e.g. 14:00). Or are we missing something?
However, we think it could be realized in ePP/DS. But my question is, could somebody please explain which heuristic, feature etc. in PP/DS we can use to accomplish this? Please find also attached an example picture.
Request clarification before answering.
Hello,
Try to go to the capacity screen in the work center CR02 and flag the option 'Can be used by several operation'. The system will allow you to put more than one operation at the same time for the same Work center.
Kind Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.