Hi all,
we run our SNP in weekly buckets and we are trying to make the optimizer block productions of the same package sizes using Setup Matrix.
We have set Setup Groups in /SAPAPO/CDPSC6 and the Setup Transitions in /SAPAPO/CDPSC7 (all possible combinations), and a Z Table that is the source for Setup ID for each product-location.

Also, assigned the Setup Matrix to the resource (production line) and changed the BADI to populated Setup ID field (from Z Table, which are being correctly assigned as per the optimizer input log, pic below)
Z table:

We are using PPMs to create production orders.
In the optimizer input log, we can see the setup time but not the setup costs, any idea why?

The setup matrix also appears assigned to the resource in input log, as we can see:

But it is not grouping the orders of the same package size as expected, to be honest, nothing is different (comparing to the status before setting up the setup matrix).
Any ideas of what we are doing wrong? If more info is necessary, please let me know.
tks
Request clarification before answering.
Hello Pedro,
Have you specified the setup matrix in the master data of a single-mixed resource or a bucket resource on the Time-Cont. Capacity
tab page ? Other resource types are not supported.
under
SAP Business Suite
SAP Supply Chain Management
SAP SCM 7.0
SAP Advanced Planning and Optimization (SAP APO)
Master Data
Application-Specific Master Data
Master Data for Production Planning
Setup Matrix
.You can find more details at:
Best regards,
Werner Hansen
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 6 | |
| 2 | |
| 2 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.