By definition a pipeline material is

Something that flows directly into the production process from a pipeline, a pipe, power transmission lines, or similar (such as oil, tap water, or electricity). Pipeline materials are not planned because they are constantly available. The price of a pipeline material is recorded in a pipeline info record for the relevant vendor. A pipeline withdrawal has the following effects: Stock levels are not changed. Consumption is updated. A pipeline liability towards the vendor is incurred that must be accounted for and settled on a periodic basis.

Pipeline materials don't generate requirements, they are not planned or procured in standard sense, i.e. with purchase orders.

Best regards