Dear experts,
Good day..
My client wants to reserve the materials once they have been assigned in a maintenance order with item category L and no body can make goods issue for the quantity committed in this maintenance order upon another maintenance order.
The system action is that the component added in the maintenance order has the status "Reserved for order" and take a reservation no., but what happened actually, it that any other maintenance order can also reserve this quantity and makes goods issue for them.
So, is there a way to make the committed quantity in any maintenance order particular for this maintenance order only not to any other one??
Thanks for your help.
Regards,
Request clarification before answering.
Hi
You can create seperate storage location where you can maintain the stock and maintain in order that storage location so that material for that order will be taken from there but other orders will not take.
Generally while creating the order, order will take defaulted storage location which is maintained in component material master. Now we have chance to keep another storage location where we can keep this required stock in there, Once you change the storage location in the order only that order can take the stock or reserve.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
| User | Count |
|---|---|
| 17 | |
| 16 | |
| 5 | |
| 3 | |
| 2 | |
| 1 | |
| 1 | |
| 1 | |
| 1 | |
| 1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.